Civic Issues
Topics getting the most attention in Urbandale public meetings, ranked by how frequently they are discussed.
8 issues in water utilities
2026 Stormwater Project public hearing
Resolution 287-2026 was scheduled to set a public hearing for the 2026 Stormwater Project covering Little Walnut Creek and Walnut Creek — flood and drainage work along both creeks.
Storm sewer easement vacation on Ridgeview Drive
The city vacated an unneeded storm sewer easement so a homeowner can build a garage addition; the city keeps the pipe in the right-of-way and the rest becomes the owner's.
Sanitary sewer connection program compliance
Some homeowners are facing extreme costs for foundation drain disconnects; council flagged a conversation on options after finding lower-priced contractors.
Aquifer storage and recovery well funding
City and water utility leaders met with Senator/Representative Nunn's office to chase federal funding for the aquifer storage and recovery facility. Drilling could be bid as early as this fall — a very deep, very expensive well.
2026 Sewer Lining Program
About 14,200 feet of aging sewer pipe will get relined for $551,715.30, shared between Urbandale and Windsor Heights sewer districts, finishing by year's end.
DART receives $20 million in federal appropriations for bus facility
DART unexpectedly received $20 million in federal funding for its new bus barn, announced at the meeting by the mayor.
Solid waste rate study and likely rate increase
The current $14.50 monthly rate doesn't cover the city's direct costs (~$14.20), before indirect costs. A cost study — and a possible shift to an enterprise fund — will likely produce a significant rate increase recommendation in late spring.
65th Street storm sewer improvements
A two-year, $2.48 million project will finally add storm sewer to 65th Street, which has none today, plus major deep storm sewer work on Meredith Drive. Meredith Drive will be closed during the first phase, with driveways and sidewalks affected as work moves along.