6 issues in water utilities with high priority
Biogas upgrading facility at wastewater plant
The city is deciding whether to build a $25 million facility that turns the biogas it currently burns off into sellable renewable natural gas. The federal tax credit could refund 25-50% of the $65 million+ project cost, with a projected payback under three years, but the system must be running by December 31, 2028. Skeptical councilmembers want updated financials before committing to more borrowing.
Frog Hollow sewer project loan notes
The Frog Hollow restoration contract came in well under the estimate, leaving about $400,000 to also stabilize the streambank through the Arboretum; work could start in April or May.
Cooling technology and water use
The Council debated whether to require closed-loop cooling, adopt industry WUE water-efficiency benchmarks, and mandate monthly water-use reporting. Iowa American Water already bills and reports usage, but the work group pushed for a water consumption ceiling in the ordinance.
Utility rate transparency and Alliant Energy practices
Councilmember Winter raised concerns that hyperscale facilities reserve huge blocks of grid power; Alliant Energy's Kiley Miller testified that MISO and the Iowa Utilities Commission require utilities to procure capacity before connection and that new customers pay 100% of their infrastructure costs.
Wastewater plant (RWRF) change orders and borrowing
Multiple speakers said the Regional Water Reclamation Facility can't even handle ADM's waste and questioned how it could handle data center cooling water; a Camanche resident described severe odors and threatened legal action.
$12 Million Note to Finish Wastewater Facility
The city is borrowing up to $12 million more through the state revolving fund to finish and commission the wastewater plant after digester start-up delays, winter boiler costs, and January and March system upsets. Expect about $10 million or less actually drawn, repaid through industrial sewer rates at roughly 5%.