$12 Million Note to Finish Wastewater Facility
Summary
The city is borrowing up to $12 million more through the state revolving fund to finish and commission the wastewater plant after digester start-up delays, winter boiler costs, and January and March system upsets. Expect about $10 million or less actually drawn, repaid through industrial sewer rates at roughly 5%.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jul 14, 2026.
Impact analysis
Up to $12 million in new debt — realistically around $10 million — repaid through industrial user rates at about 5% interest.
Ratepayers and industrial users get a fully operational treatment plant; contractors get paid for completed work.
Mentions & discussions (3)
Regular City Council - Jul 14 2026
A drawable note will cover remaining construction costs for the Regional Water Reclamation Facility tied to the ADM project, repaid through the new industrial sewer rate rather than general taxes.
Regular City Council - May 12 2026
The city is borrowing up to $12 million more through the state revolving fund to finish and commission the wastewater plant after digester start-up delays, winter boiler costs, and January and March system upsets. Expect about $10 million or less actually drawn, repaid through industrial sewer rates at roughly 5%.
Regular City Council - Apr 28 2026
The council set the hearing date for authorizing up to $12 million in taxable general obligation capital loan notes to finish wastewater treatment plant contracts, targeting full operational flow by about June 1.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Clinton
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.