$12 Million Note to Finish Wastewater Facility

Summary

The city is borrowing up to $12 million more through the state revolving fund to finish and commission the wastewater plant after digester start-up delays, winter boiler costs, and January and March system upsets. Expect about $10 million or less actually drawn, repaid through industrial sewer rates at roughly 5%.

At a glance