11 issues in water utilities
Young Arena and stormwater infrastructure bids
The council was scheduled to set bid openings and hearings for replacing Young Arena's chiller and condenser and for the Delane Avenue stormwater detention project.
Storm sewer disconnects and Broadway reconstruction
Kern Street storm sewer work will temporarily close part of Broadway in stages. The bid came in nearly $31,000 under the engineer's estimate.
Nevada Street Emergency Sewer Bypass Pumping
The city approved nearly $225,000 to rent and remove bypass pumping equipment for an emergency sanitary sewer repair at the dead end of Nevada Street.
Eastside Interceptor Sewer Repairs
The waste management plant needed $21,398.50 in emergency switchgear repairs after a power outage. Keeping the sewer treatment plant running protects public health and avoids costlier failures.
Emergency sewer repairs on Nevada Street
The 54-inch sanitary interceptor failed and the city is renting bypass pumping equipment and sealing new manholes as part of the emergency fix. Those rentals and sealings were approved tonight, running well over $100,000 combined.
Refuse cart replacement
The Sanitation Department is getting 559 brown and 200 green refuse carts. Residents with worn-out carts should see replacements in circulation.
Wastewater plant electrical upgrades
A $302,000 contract amendment moves forward electrical updates at the wastewater treatment plant — a lightning strike last summer revealed the plant could lose power redundancy, and the work adds arc-flash protection.
Well monitoring and nitrate concerns
Council members Morrow and Creighton-Smith raised concerns about monitoring city wells for chemicals and nitrates, citing Iowa's high cancer rates — residents in Ward 3 pushed for stronger monitoring.
River wall restoration design
The council approved up to $196,500 for design work to restore the downtown river wall and fix floodwall safety tie-offs; no federal money is available for this stretch.
Virden Creek Dam and Fletcher Gate repairs
The committee added $2.63 million to the FY 2027 budget for repairing the Virden Creek Dam and Fletcher Gate. It's the largest single budget action of the meeting.
Raw Wastewater Treatment Plant rehab
The committee approved $94,540 for rehab and building upgrades at the Raw Wastewater Treatment Plant. This keeps the plant's facilities in working order, which matters for everyone on the city sewer system.