Summary

The city is seeking a $100,000 state grant toward a $332,000 full rehab of 7025 Douglas Avenue — the beloved old Dairy Queen — into retail space anchoring the future downtown plaza.

At a glance

Total mentions
9
Last 30 days
0

Last discussed Sep 15, 2026.

Impact analysis

💰Financial impact

About $332,000 total, offset by up to $100,000 in grant funds, with city CIP funds already committed.

✅Who benefits

Downtown Urbandale businesses, pedestrians and residents who have asked for the Dairy Queen building's return.

⚠️Who could be affected

Drivers used to two through lanes may see slightly slower peak travel until signal timing is optimized.

Mentions & discussions (10)

MeetingSep 15, 2026

City Council - September 15, 2026

The council leased two city-owned downtown buildings: a former Dairy Queen to a gelato shop operator and a three-year extension to Big Sky Bread. Both leases include percentage rent and come with city-funded improvements meant to activate the 'Big Block' area of the downtown master plan.

MeetingAug 11, 2026

City Council Lunch & Learn - August 11, 2026

Consultants are testing cross-sections for Douglas Avenue — sidewalk zones, street lighting, planter placement, and angled vs. parallel parking — to figure out how to fit pedestrians, utilities, and parking into the existing right-of-way.

MeetingJul 21, 2026

City Council - July 21, 2026

The city unveiled a new downtown brand built around its trolley-line history and a 'rediscovery' theme, aiming to give residents a 'third place' to linger downtown. It will roll out at the October 10 pop-up park event, with a logo, partner toolkit, and brand guide to follow.

MeetingJul 7, 2026

City Council - July 7, 2026

Douglas Avenue downtown will be restriped into a three-lane section with new on-street parking and painted bump-outs by mid-October, plus a plaza upgrade at the Big Block ahead of the October 10 block party. Signal timing improvements from 128th Street eastward follow later.

MeetingJun 1, 2026approved

City Council - June 1, 2026

The consent agenda awarded the contract for phase 1 of the Big Block interior commons and public amenity area, prepping the space for future pop-ups. Councilmembers also heard updates on the Douglas Avenue streetscape project at community meetings.

MeetingApr 7, 2026

City Council Special Meeting - April 7, 2026

The city is seeking a $100,000 state grant toward a $332,000 full rehab of 7025 Douglas Avenue — the beloved old Dairy Queen — into retail space anchoring the future downtown plaza.

MeetingMar 17, 2026

City Council - March 17, 2026

The city refreshes its TIF districts every few years to keep incentive and project schedules current. Westover's standard incentive got trimmed from five years to four, and downtown lost its standard rebate in favor of customized deals for revitalization projects.

MeetingFeb 3, 2026

City Council - February 3, 2026

The city hired consultants to rewrite downtown zoning (about $124,000) and create a downtown brand identity — steps toward making downtown Urbandale a walkable, investable mixed-use district envisioned in the master plan.

MeetingJan 13, 2026

City Council Lunch & Learn - January 13, 2026

The city is buying up key downtown properties, planning a plaza and Douglas Avenue redesign, and running RFPs for a downtown zoning code and branding to spark private investment. Staff say this is a decades-long effort starting with visible wins in the 'big block' on 70th–71st.

KCCIJun 18, 2024

Urbandale City Council to hold vote on downtown renovation

Urbandale City Council to hold vote on downtown renovation KCCI

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Urbandale

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.