The council adopted a $211.65 million five-year building plan covering streets, parks, police headquarters and fire stations, with about $35.5 million hitting the 2026 construction year. Changes made the sustainability intent for the police station and Fire Station 41 explicit and moved the rec hub project to 2027.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jan 6, 2026.
Impact analysis
$211.65 million over five years, with about $35.5 million spent in 2026.
Residents get upgraded streets, parks, and safety facilities across the city over the next five years.
Resident Tim Fitzgerald argued taxpayers bear rising bond debt and interest costs from incremental project spending.
Mentions & discussions (1)
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Urbandale
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.