142nd Street paving joint project with Grimes
Summary
A $5.56 million reconstruction of 142nd Street, shared with Grimes, was awarded with Urbandale's share about $5.2 million — but the street will be closed most of the construction season. Lower bids dropped property owner assessments and eliminated prior assessment deficiencies.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Feb 3, 2026.
Impact analysis
Urbandale's share is about $5.2 million; property owner assessments dropped from $90 to $65.75 per square yard for paving.
Residents and developers in the western growth area gain a major paved collector.
Residents and properties along 142nd Street face most-of-season road closures in 2026.