HighWater Utilities

Storm and sanitary sewer separation grant applications

Spencer still has five areas where storm and sanitary sewers are combined — a big reason flooding hits sewage systems. Three applications totaling about $12.7 million would finish the job, with state awards expected early 2027. Public hearings come first.

5 mentions (2 this month)Last discussed Oct 19, 2026
HighWater Utilities

Lead service line replacement

About 240 Spencer properties will get lead or galvanized water service lines replaced starting August, run through SMU and finished by September 2027. Most lines will be bored in to keep the digging minimal, and affected owners have already been notified and signed easements.

4 mentions (1 this month)Last discussed Oct 19, 2026
HighWater Utilities

Upcoming Sewer Rate and Flood Insurance Decisions

Engineers have inspected 1,200 of 1,450 manholes with smoke testing starting July 27. Meanwhile, the city and PFM will restart the wastewater fee conversation this fall — fees are what pay the debt on sewer projects.

3 mentions (1 this month)Last discussed Oct 5, 2026
HighWater Utilities

Wastewater treatment project costs

Council asked the city manager to compare notes with other Iowa cities facing the same problem: bids on big wastewater projects coming in above engineer estimates, with rebids often even higher. Spencer's smaller projects are pricing lower, but large capital-intensive ones are running high.

1 mentionLast discussed Sep 21, 2026
MediumWater Utilities

2026 AV-Gas Fuel System Project

The board compared its fuel flowage fee to a 0.0078 average and wants another month to study where the fee stands and how changes would affect reserves.

2 mentionsLast discussed Aug 10, 2026
MediumWater Utilities

Storm sewer study engineering payment

The bills list includes a $198,032.80 payment to McClure Engineering for the storm sewer study.