W 18th Street trail segment
Summary
A new trail segment will be built this fall, and the city patched up its expired cost-sharing agreement with Clay County for the West 18th Street bridge replacement, now running through 2027.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Aug 3, 2026.
Impact analysis
Trail construction costs $73,737.50; the bridge project cost sharing with the county continues.
Trail users and west-side drivers who rely on the 18th Street bridge.
Two property owners adjacent to the trail segment were directly impacted, though they were notified by certified mail.
Mentions & discussions (3)
City Council - Aug 3, 2026
A new trail segment will be built this fall, and the city patched up its expired cost-sharing agreement with Clay County for the West 18th Street bridge replacement, now running through 2027.
City Council - Jul 6, 2026
Plans and specs for the trail segment between Country Club Lane and 24th Avenue West were approved; bids open July 27 and construction follows soon after.
General - Jun 15, 2026
The trail project's public hearing is set for July 6, with bidding and an award targeted for early August and completion by late October. The splash pad is taking shape, with underground piping mostly done and concrete work coming.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Spencer
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.