The city awarded a roughly $1.14 million contract to replace about 2,600 feet of aging water main along Elm Avenue and Snyder Street — about 9% under the engineer's estimate, which is good news for ratepayers.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed May 21, 2026.
Impact analysis
Contract at $1,137,500, about 9% under a roughly $1.5 million budget.
Founders district residents and businesses with more reliable water service and fire flow.