Forevergreen Road/Jasper Avenue Roundabout
Summary
The roundabout project is moving fast — a third of Jasper Avenue was paved last week with more this week, and the west leg toward Tiffin is done. Substantial completion is expected mid-November.
At a glance
- Total mentions
- 8
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 22, 2026.
Impact analysis
North Liberty's share is roughly $3.5 million of the $5.06 million contract.
Commuters and residents traveling the Forevergreen/Jasper corridor.
Commuters and parents near the junior high face continued congestion in the near term.
Mentions & discussions (8)
City Council - Sep 22, 2026
The roundabout project is moving fast — a third of Jasper Avenue was paved last week with more this week, and the west leg toward Tiffin is done. Substantial completion is expected mid-November.
City Council - Aug 11, 2026
Paving at the Forevergreen/Jasper roundabout is expected by the end of the month, with traffic control adjusted to ease congestion. The Forevergreen Road connection to Coralville was celebrated at a recent groundbreaking.
Planning Commission - Jul 7, 2026
Commissioners flagged that Forevergreen Road is already congested, especially during school pickup at North Central Junior High. Staff pointed to Coralville's long-term concept plans for a roundabout at Forevergreen and Front Street, though nothing is funded for construction yet.
City Council - Jun 23, 2026
The council approved a change order and second pay application for the roundabout project, keeping construction moving.
City Council - May 12, 2026
Temporary road paving starts late May, with detours around the roundabout intersection through the summer. Expect trickier driving starting in June; the Penn Street ramp closure may also come early.
City Council - Apr 14, 2026
The city engineer updated the council on the North Stewart Street project and the Forevergreen Road/Jasper Avenue roundabout.
City Council - Jan 27, 2026
The city accepted a $5.06 million bid from CJ Moyna & Sons — $1.6 million under estimate — for the roundabout project, which it shares with Tiffin (Tiffin pays about $1.5 million of the cost).
City Council - Jan 13, 2026
A $3.9 million roundabout at Forevergreen and Jasper, cost split with Tiffin, plus a $2.7 million Jasper Avenue rebuild. Construction starts this spring, so drivers should expect construction staging and traffic impacts.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for North Liberty, IA
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.