Centennial Park Phase 2 Construction

Summary

The council accepted the bid and authorized the contract for the splash pad phase of the Centennial Park event complex. City Engineer Bilskemper indicated completion by April 2027.

At a glance

Total mentions
8
Last 30 days
0

Discussed at 2 meetings in the last 60 days; most recently Oct 1, 2026.

Impact analysis

๐Ÿ’ฐFinancial impact

Costs set by the accepted bid and executed contract.

โœ…Who benefits

Families and residents who will use the new splash pad and event complex amenities.

Mentions & discussions (9)

MeetingOct 1, 2026

Parks & Recreation Commission - Oct 1, 2026

The splash pad is running about two months behind after the state health department required a redesign so water flows outward from the youth zone, adding a perimeter drain. A Memorial Day opening is unlikely.

MeetingSep 22, 2026

City Council - Sep 22, 2026

Another pay application went to Conlon Construction for Centennial Park Phase 2 โ€” the park expansion keeps progressing.

northlibertyiowa.govJul 20, 2026

Centennial Park

Centennial Park northlibertyiowa.gov

MeetingJun 23, 2026

City Council - Jun 23, 2026

The city received a $1.246 million check from the Community Foundation of Johnson County; about $2.5 million total has been raised for the community center project, with phases 3 and 4 still seeking donations.

MeetingJun 4, 2026

Parks & Recreation Commission - Jun 4, 2026

Phase 2 of the Centennial Park splash pad has officially begun, with contractors locating utilities and documenting progress.

MeetingMar 24, 2026approved

City Council - Mar 24, 2026

The council accepted the bid and authorized the contract for the splash pad phase of the Centennial Park event complex. City Engineer Bilskemper indicated completion by April 2027.

MeetingMar 10, 2026approved

City Council - Mar 10, 2026

The council gave final approval to the splash pad plans โ€” about 8,000 square feet with a water journey tide pool under an inch deep, restrooms, picnic shelter and reclaimed water with UV treatment. No lifeguards or concessions, but you can bring your own picnic.

MeetingMar 5, 2026

Parks & Recreation Commission - Mar 5, 2026

Parks staff are working with design firm Shive Hattery on the splash pad planned for Centennial Park. Design is still in progress, so residents can expect more details as the project moves forward.

MeetingJan 13, 2026

City Council - Jan 13, 2026

South Slope gives $75,000 toward the Next Stage project and helps land an interest-free USDA loan; in return, the rock playground gets the South Slope name.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for North Liberty, IA

What the council decided, in plain English โ€” one email a week.

Free. Unsubscribe with one click any time. We never sell your email.