Summary
The roads department's new satellite facility cleared zoning with a special use permit, and a public hearing on construction plans is set for March 30 with spring bidding to follow.
At a glance
- Total mentions
- 7
- Last 30 days
- 0
Last discussed Jul 6, 2026.
Impact analysis
Construction contract will be bid this spring; cost estimate comes out at the March 30 hearing.
Secondary Roads staff get modern, well-located equipment storage for the next 50-75 years.
Taxpayers pick up the debt service through the levy.
Mentions & discussions (7)
Board of Supervisors — board of supervisors — 2026-07-06
The county is borrowing $225,000 at 3.75% from CBI Bank & Trust to build and equip a satellite building for the County Engineer's Office, repaid over five years through a property tax levy.
Board of Supervisors — board of supervisors — 2026-06-15
Construction bids came in higher than expected, so the county is borrowing up to $225,000 to finish the satellite building for the County Engineer's Office. Lender proposals are due June 29.
Board of Supervisors — board of supervisors — 2026-06-08
The county locked in a $893,507 contract with Daxon Construction for the new engineer satellite facility, with construction expected to start this year.
Board of Supervisors — board of supervisors — 2026-06-01
The lowest of six construction bids came in at $893,507 for a new engineer's satellite building, and the county will consider borrowing $225,000 toward the roughly $975,000 project at a June 15 hearing — estimated at about 47 cents a year on a $100,000 home.
Board of Supervisors — board of supervisors — 2026-05-18
Bids for the new secondary roads shop on Independence Avenue came in about $225,000 over the 2023 bond amount. A new state law raised the project cap to $975,000, so the county plans to rebond and bridge the cash until it hits next year's debt levy.
Board of Supervisors — board of supervisors — 2026-03-30
The county is building a prototype satellite shed on 2445 Independence Ave for graders and snow plows, replacing the worst-condition facility (Funk Hills). It will serve as a model for future facility replacements, with bids due April 23 and announced April 27.
Board of Supervisors — board of supervisors — 2026-03-09
The roads department's new satellite facility cleared zoning with a special use permit, and a public hearing on construction plans is set for March 30 with spring bidding to follow.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Muscatine County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.