Center Street Viaduct Rehabilitation and Railing Replacement
The viaduct will close for 120 working days starting April 6 as Boulder Contracting does $4.05 million in repairs — about $750,000 over estimate. It will almost certainly still be closed during RAGBRAI in July, and the council wants a cost comparison on swapping the historic railing for black fencing.
Five-Year Street Improvement Program Funding
Council members pushed for a public, street-by-street schedule showing when roads will be fixed. Staff are building a pavement management plan with a consultant, expected in outline form around August or September.
2026 Street Rehabilitation Project
Multiple residents pleaded for street repairs, citing potholes, a sinkhole that stranded a snowplow, and questions about where gas-tax street money has gone for six years.