HighRoads

Center Street Viaduct Rehabilitation and Railing Replacement

The viaduct will close for 120 working days starting April 6 as Boulder Contracting does $4.05 million in repairs — about $750,000 over estimate. It will almost certainly still be closed during RAGBRAI in July, and the council wants a cost comparison on swapping the historic railing for black fencing.

20 mentionsLast discussed Sep 14, 2026
HighRoads

Five-Year Street Improvement Program Funding

Council members pushed for a public, street-by-street schedule showing when roads will be fixed. Staff are building a pavement management plan with a consultant, expected in outline form around August or September.

2 mentionsLast discussed Sep 14, 2026
HighRoads

2026 Street Rehabilitation Project

Multiple residents pleaded for street repairs, citing potholes, a sinkhole that stranded a snowplow, and questions about where gas-tax street money has gone for six years.

9 mentionsLast discussed Jul 27, 2026
MediumRoads

2nd Avenue Sidewalk Dispute

Property owner Tom Deimerly pressed the council over a broken sidewalk he's being asked to pay for and a pedestrian alley conversion that could block furniture deliveries to his 210 East Main Street building. The council voted 4-3 to proceed with the alley and defer the sidewalk to Phase 8.

4 mentionsLast discussed Apr 27, 2026
HighRoads

4-way stop at Merle Hibbs and South 6th Street

Residents pushing for a four-way stop at Merle Hibbs Boulevard and Sixth Street were frustrated the item slipped to March 23, arguing crash counts and traffic studies miss real conditions like downhill speeds and viaduct detour traffic.

8 mentionsLast discussed Mar 23, 2026
MediumRoads

Railroad quiet zone corridor safety

A resident urged the city to finish its railroad quiet zone work with full engineering treatments — medians, gates, circuitry — rather than shortcuts, building on the closed Second Street crossing and the $750,000 UP contribution.

2 mentionsLast discussed Mar 9, 2026
HighRoads

Downtown Alley Improvements

Leftover money from the downtown East Main/Center Street reconstruction project will now pay for alley repairs nearby. Three council members and several residents argued streets should come first, and questions were raised about where street repair money has gone.

3 mentionsLast discussed Mar 9, 2026
LowRoads

On-street angle parking

A push to standardize head-in vs. back-in angle parking citywide went nowhere — the council decided to leave signs and pavement markings as they are and handle any changes one block at a time.