City Hall Space Utilization and Future
Summary
A new study says moving all city staff into the Carnegie and Parks & Rec buildings would cost roughly $985,000–$1.1 million, versus investing in the aging original City Hall's failing shared boiler. Council wants a full cost-and-operating comparison before choosing a path — and any big bond could trigger a reverse referendum.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 13, 2026.
Impact analysis
Up to roughly $1.1 million in construction, plus furniture and soft costs, likely requiring bonding.
City staff and visitors would get safer, more functional workspace; a buyer could reuse the historic building.