Pleasant Grove Road reconstruction progress

Summary

The county awarded the contract to pave Pleasant Grove Road from Iowa City Road to Mediapolis Road. The project was designed and surveyed in-house, saved money through competitive bidding, and should start next spring. Drivers will eventually get a paved route instead of the current surface.

At a glance

Total mentions
13
Last 30 days
1

Discussed at 4 meetings in the last 60 days; most recently Nov 17, 2026.

Impact analysis

💰Financial impact

The low bid came in around $2.23 million, roughly $55,000 under the engineer's estimate.

✅Who benefits

Travelers and local residents who use Pleasant Grove Road will get a safer, paved route.

⚠️Who could be affected

Road will be closed during construction, though timed to avoid harvest; some drainage changes concern nearby residents.

Mentions & discussions (13)

MeetingNov 17, 2026approved

Board of Supervisors — board of supervisors — 2026-11-17

The county awarded the contract to pave Pleasant Grove Road from Iowa City Road to Mediapolis Road. The project was designed and surveyed in-house, saved money through competitive bidding, and should start next spring. Drivers will eventually get a paved route instead of the current surface.

MeetingOct 13, 2026

Board of Supervisors — 2026-10-13

The current Pleasant Grove Road project is nearly done and could open this week; the next phase goes out for bid this month with construction likely next spring. A resident also flagged water repeatedly washing over 85th Avenue onto her property — the engineer will investigate whether a long-removed culvert is the culprit.

MeetingSep 29, 2026

Board of Supervisors — 2026-09-29

Rain keeps slowing the Pleasant Grove Road paving project; bids for the next 1.5-mile phase (Iowa City Rd. to Big Hollow) go out October 29. Farmers dragging mud onto roads this fall is a driving hazard — and a liability for the farmers.

MeetingSep 22, 2026

Board of Supervisors — board of supervisors — 2026-09-22

The county poured 1.2 miles of new concrete on Pleasant Grove Road in two marathon days, though the road remains closed to through traffic. The Iowa City Road intersection should reopen within days, and design work is moving on the next 1.5-mile segment with bids possibly in late October.

MeetingSep 15, 2026

Board of Supervisors — board of supervisors — 2026-09-15

Rain is delaying the concrete pour on the Pleasant Grove project, which could push the timeline back a few days. The project tour may move to next week.

MeetingSep 8, 2026

Board of Supervisors — board of supervisors — 2026-09-08

The Pleasant Grove project is moving forward — the Iowa City Road intersection closed Friday and will be shut for less than three weeks while concrete is torn out and poured. Drivers should also watch for slow farm equipment and washboarding on gravel roads.

MeetingAug 25, 2026

Board of Supervisors — 2026-08-25

The Pleasant Grove Road intersection with Iowa City Road closes next week for up to three weeks, with a gravel detour, as the paving project advances. The next phase to Big Hollow Road is being designed for bid this fall.

MeetingAug 18, 2026

Board of Supervisors — board of supervisors — 2026-08-18

The Pleasant Grove Road project continues despite rain delays; the Iowa City Road/Pleasant Grove Road intersection is expected to close the week of August 31 for up to three weeks. Truck drivers following GPS onto mud roads have caused extra towing headaches.

MeetingJun 23, 2026

Board of Supervisors — 2026-06-23

The Pleasant Grove Road project is stalled by wet weather and downed power lines, and the Engineer is asking folks to call in holes appearing on saturated roads.

MeetingMay 26, 2026

Board of Supervisors — 2026-05-26

Pleasant Grove Road closes Monday from Iowa City Road to Highway 61, likely until September. Commuters who use it to avoid the Mediapolis interchange construction will need alternate routes.

MeetingMay 12, 2026

Board of Supervisors — board of supervisors — 2026-05-12

Pleasant Grove Road between Iowa City Road and Highway 61 fully closes in early June, with detours pushing traffic onto 190th and 140th, which get dust control. Crack sealing on the Mediapolis blacktop starts this week; the 151st Street culvert is in but the road isn't open yet.

MeetingMar 3, 2026

Board of Supervisors — board of supervisors — 2026-03-03

The first phase of Pleasant Grove Road paving came in about $500,000 under estimate, so the engineer wants to redirect funds and budget room to bid another ~1.5-mile, roughly $2 million segment next winter while contractor competition holds prices down.

MeetingJan 27, 2026

Board of Supervisors — board of supervisors — 2026-01-27

Roughly 1.2 miles of Pleasant Grove Road from Highway 61 — including the Iowa City Road intersection — will be paved for $1.497 million, about $400,000 under estimate, with no curbs by design to preserve farm drainage.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Des Moines County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.