Secondary roads progress
Summary
The board advanced four road items: the 288th Trail paving with Adel (~$690K total, county share ~$116K), the H Avenue bridge replacement, five box culverts, and a federal classification cleanup tied to Van Meter development and Laredo Trail paving needs. All bids come March 24.
At a glance
- Total mentions
- 5
- Last 30 days
- 0
Last discussed Sep 15, 2026.
Impact analysis
Roughly $690,000 for 288th Trail (county share ~$116,000), plus bridge and culvert packages to be bid.
Adel-area commuters, H Avenue residents freed from the bridge weight limit, and haulers using county roads.
Travelers will face road closures on F90 and around active construction zones starting mid-May.
Mentions & discussions (5)
Board of Supervisors Agenda and Minutes - Sep 15, 2026
F90 repaving is basically done, two bridges should open within weeks, box culverts are in, and Booneville-area bridge work starts September 23 with a full closure until mid-March.
Board of Supervisors Agenda and Minutes - May 5, 2026
A busy season ahead: B Avenue and H Avenue bridge replacements, F-90 paving toward Van Meter, 288th Street paving, five box culverts, and a 347th Street bridge rehab closing for much of the summer.
Board of Supervisors Agenda and Minutes - Mar 17, 2026
Laredo Trail paving was added to this year's program, the Highway 6 turn lanes project goes to bid April 28, and bridges, culverts, and the B Avenue Bridge and F90 projects kick off around mid-May. Expect road closures across the county.
Board of Supervisors Agenda and Minutes - Mar 3, 2026
The new Secondary Roads office and garage are about 90% done — heat and lights on, county crews starting concrete work this month.
Board of Supervisors Agenda and Minutes - Feb 24, 2026
The board advanced four road items: the 288th Trail paving with Adel (~$690K total, county share ~$116K), the H Avenue bridge replacement, five box culverts, and a federal classification cleanup tied to Van Meter development and Laredo Trail paving needs. All bids come March 24.
Related development
County Attorney — 902 Court Renovations
Gives prosecutors a modern, purpose-built home with training space — at a fraction of the cost of new construction — funded from the capital fund.
Auditor — 100 Nile Kinnick Dr N & 210 N 10th St Renovations
Creates dedicated early-voting space for a county where 11,000 people voted in person in 2024, plus secure equipment storage — while raising questions about historic-district exterior rules.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Dallas County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.