Five-year road construction program and budget
Summary
The Board tweaked the county's road construction plan, adding five culvert replacements and a paving project on 288th Trail, and pulling the F90 widening project forward a year. Total program cost now tops $50.4 million.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Mar 31, 2026.
Impact analysis
Program total rises about $1.4 million, with the local fund share up $875,770.
Drivers on 200th Street, 335th Street, Sportsmans Club Road, 288th Trail, and F90 get safer, better-maintained roads.
Mentions & discussions (3)
Board of Supervisors Agenda and Minutes - Mar 31, 2026
The board formally adopted the five-year plan guiding county road and bridge work after a continued public hearing.
Board of Supervisors Agenda and Minutes - Jan 27, 2026
The Board tweaked the county's road construction plan, adding five culvert replacements and a paving project on 288th Trail, and pulling the F90 widening project forward a year. Total program cost now tops $50.4 million.
Board of Supervisors Agenda and Minutes - Jan 12, 2026
Road maintenance is getting more expensive — gravel and limestone prices have nearly doubled, and bridge repair projects will cross fiscal years. The county may share paving costs with cities.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Dallas County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.