Courthouse and county office renovations
Summary
The courthouse renovation may be substantially complete, and the board was set to consider bids and price amendments for renovating the County Attorney and Auditor offices. These projects determine what county facilities residents and staff will work in for decades.
At a glance
- Total mentions
- 19
- Last 30 days
- 2
Rising — discussed at 5 meetings since Sep 22, 2026, up from 2 in the two months before.
Impact analysis
Guaranteed maximum price amendments and bid awards directly affect construction costs paid from county funds.
County residents get improved courthouse and office facilities and more functional public services.
County taxpayers, who absorb the overage and the delay.
Mentions & discussions (19)
Board of Supervisors Agenda and Minutes - Nov 17, 2026
The county is moving ahead with renovating the Auditor's Office, with the first contractor pay application (about $38,825) and a change order up for approval.
Board of Supervisors Agenda and Minutes - Nov 10, 2026
The courthouse renovation may be substantially complete, and the board was set to consider bids and price amendments for renovating the County Attorney and Auditor offices. These projects determine what county facilities residents and staff will work in for decades.
Board of Supervisors Agenda and Minutes - Oct 6, 2026
The courthouse renovation is 91% done and on track to wrap up by the end of October. Court has already started hearing cases on level 2, and sidewalks and sod replacement are underway outside.
Board of Supervisors Agenda and Minutes - Sep 29, 2026
Floor box cables for the new county attorney satellite office in courthouse Room 202 were severed. Staff are working with Turner to find out why and restore service.
Board of Supervisors Agenda and Minutes - Sep 22, 2026
Heavy rain exposed roof leaks in the Auditor's Office at 210 North; patches are holding for now but re-roof quotes are coming for the 1963 building that will house $1.5-2 million in equipment during the remodel.
Board of Supervisors Agenda and Minutes - Sep 8, 2026
The County Attorney and Auditor's office renovation project advanced with a pre-qualified bidder pool of 29 contractors across four trade packages. Bid documents go out Friday, bids come back late September, and a guaranteed maximum price lands before the board in late October.
Board of Supervisors Agenda and Minutes - Aug 4, 2026
The historic courthouse remodel is 83% done — new sod outside, the second-floor jury courtroom finished, and level three framing underway.
Board of Supervisors Agenda and Minutes - Jul 21, 2026
Design moved forward with a new early-voting vestibule, relocated emergency generator, and added accessible parking. Fire suppression for the $700,000+ election equipment building remains a live debate.
Board of Supervisors Agenda and Minutes - Jul 14, 2026
The board was scheduled to see a design development presentation and budget estimate for renovating the Auditor's Office — a county courthouse capital project. The budget estimate deliverable is the number residents will want to know, since capital projects affect county budgets and taxes.
Board of Supervisors Agenda and Minutes - Jun 30, 2026
The 902 Court renovation estimate jumped to $4.4 million before value engineering brought it back to about $3.7 million. Key savings: keeping the existing roof (15 more years of life), a cheaper HVAC design with individual thermostats, and J-hooks instead of cable tray.
Board of Supervisors Agenda and Minutes - Jun 16, 2026
The county is paying up to $107,000 to remove asbestos in the Wells Fargo building being renovated for the auditor's office. A resident urged the county attorney to review whether the purchase agreement's disclosure terms offer any recourse.
Board of Supervisors Agenda and Minutes - Jun 9, 2026
Hidden structural surprises in the old courthouse just cost taxpayers another $206,941 and pushed occupancy to mid-to-late October 2026. Workers had to add steel because there were no original drawings to warn them the walls they removed were load-bearing.
Board of Supervisors Agenda and Minutes - Jun 2, 2026
The courthouse remodel is 69% done; extra structural steel and shoring are needed to open up the fourth-floor jury courtroom, but the finished floor load limit will be unchanged. The board approved a $451,574 monthly payment.
Board of Supervisors Agenda and Minutes - May 26, 2026
The county hired Turner Construction to manage the Auditor's office renovation after a competitive selection run by the Farnsworth Group. Turner topped the scoring of five construction firms, so the long-planned courthouse building project now moves into execution.
Board of Supervisors Agenda and Minutes - Mar 17, 2026
The courthouse is getting $216,241 in foundation waterproofing and drain tile work starting mid-April, with some sidewalk closures around the building. It should wrap up by early June.
Board of Supervisors Agenda and Minutes - Mar 10, 2026
Design work is moving ahead on the County Attorney office renovation at 902 Court and the auditor office renovations at 100 Nile Kinnick Dr N and 210 N 10th St. Construction could start as early as July at 902 Court. These projects are paid for with bond funds already approved.
Board of Supervisors Agenda and Minutes - Mar 3, 2026
The board agreed to renovate 902 Court for the County Attorney and the Wells Fargo/210 N. 10th buildings for the Auditor — saving about two-thirds the cost of the failed criminal court building plan — but the Auditor pushed to at least compare a new-building option.
Board of Supervisors Agenda and Minutes - Feb 24, 2026
The county's consultant showed a plan to renovate 902 Court for the County Attorney's office — about 23,400 square feet, room for 42 staff over 30 years, and a mock trial courtroom instead of a fitness center. It's estimated at $3.7 million, much cheaper than the attorney's share of the old criminal courts plan. No decision yet.
Board of Supervisors Agenda and Minutes - Feb 3, 2026
Four big county construction projects were on the agenda: the Secondary Roads admin addition, courthouse renovation, evidence storage and firing range, and the Adel EMS station. Pay applications and contingencies were up for review, and a Turner Construction agreement for the EMS station was scheduled for consideration. These buildings shape county services and budgets for decades.
Related development
Auditor — 100 Nile Kinnick Dr N & 210 N 10th St Renovations
Creates dedicated early-voting space for a county where 11,000 people voted in person in 2024, plus secure equipment storage — while raising questions about historic-district exterior rules.
County Attorney — 902 Court Renovations
Gives prosecutors a modern, purpose-built home with training space — at a fraction of the cost of new construction — funded from the capital fund.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Dallas County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.