B Avenue bridge project
Summary
Herberger Construction won the B Avenue bridge job at about $698,000 — a little over estimate due to material prices, with 60 working days starting no later than May 17.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Sep 1, 2026.
Impact analysis
$698,486.36, about 2% above the engineer's estimate.
Residents who use B Avenue get a rebuilt, safer bridge.
Local traffic will deal with construction-period closures or detours.
Mentions & discussions (3)
Board of Supervisors Agenda and Minutes - Sep 1, 2026
Four big county building projects are wrapping up or starting: courthouse renovations are 88% done with court resuming next week, the evidence storage and firing range is 95% finished, and the Adel EMS station is just beginning. The board approved nearly $1.05 million in construction payments.
Board of Supervisors Agenda and Minutes - May 5, 2026
Four big county building projects are moving: the Secondary Roads addition is 97% done with staff moved in, the courthouse is 61% complete, the evidence storage/firing range is 61% done, and the Adel EMS station is just starting. The Board approved about $1.78 million in construction payments in one morning.
Board of Supervisors Agenda and Minutes - Mar 3, 2026
Herberger Construction won the B Avenue bridge job at about $698,000 — a little over estimate due to material prices, with 60 working days starting no later than May 17.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Dallas County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.