Thrush Avenue and 160th Street project schedules
Summary
The county is signing a corrected federal-aid funding agreement for Thrush Avenue. The letting is set for August, but paving likely won't start until next spring because of the November 15 cutoff.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 28, 2026.
Impact analysis
Federal aid will help cover the paving cost, though the county's share wasn't spelled out.
Drivers who use Thrush Avenue will eventually get an improved paved road.
Mentions & discussions (3)
Board of Supervisors — board of supervisors — 2026-09-28
The Thrush Avenue federal-aid project probably won't be finished this fall because of the weather — it'll likely wait until spring. The 160th Street large structure is still on track, with the contractor moving in at the end of October and working into cold weather with heated concrete if needed.
Board of Supervisors — board of supervisors — 2026-05-18
About 6.5 miles of Thrush Avenue from 190th Street north to the Mason City limits will be repaved with federal STP funding, including an attempt to fix the rough dip where the DOT's concrete approach ends on the north end.
Board of Supervisors — board of supervisors — 2026-04-06
The county is signing a corrected federal-aid funding agreement for Thrush Avenue. The letting is set for August, but paving likely won't start until next spring because of the November 15 cutoff.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Cerro Gordo County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.