N Ankeny Boulevard & NW Reinhart Drive traffic signal
Summary
A new signal and turn lanes are coming to a busy intersection monitored since 2021, awarded at $508,033 — 16% under estimate. Construction starts around May 2027 with detours through Georgetown Boulevard, Ash Drive and Oak Drive during roughly three months of work.
At a glance
- Total mentions
- 2
- Last 30 days
- 2
Discussed at 1 meeting in the last 60 days; most recently Nov 16, 2026.
Impact analysis
The city budgeted $630,000 for construction; the winning bid saves roughly $100,000 against that, with some costs reimbursed by Central Bank.
Drivers and pedestrians at a growing northwest intersection, plus Central Bank-area development traffic.
Drivers using the detour routes during construction; residents raised concerns about speeding on cut-through streets.
Mentions & discussions (2)
City Council - Nov 16, 2026
A new signal and turn lanes are coming to a busy intersection monitored since 2021, awarded at $508,033 — 16% under estimate. Construction starts around May 2027 with detours through Georgetown Boulevard, Ash Drive and Oak Drive during roughly three months of work.
New SE Oralabor Road & SE Four Mile Drive Traffic Signal to be Activated Friday, Nov. 13
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Ankeny, IA
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.